During the Holidays the old library and two classrooms disappeared and were relocated up near the back gate | ![]() |
|
|
|
![]() Late October The builders used a special tool to get everything level and some of the men layed the concrete blocks for the bottom of the building. |
![]() A Few Days Later ... A concrete pump arrived to move the concrete from the trucks down to make the ground floor of the new building |
![]() That Same Day ... Even though it rained, a whole gang of men spread the concrete and smoothed it out over the steel reinforcing mesh. |
![]() The Next Day The builder cut up the timber and started making the frames for the ground floor walls. |
![]() Two Days Later ... Mr McIntyre came to inspect the building progress every morning and found the walls were nearly finished. |
![]() Mid November In spite of all the rain, the wall frames were finished and heavy steel beams were lifted in by a crane to hold up the next floor. |
![]() A Week Later The upstairs floor was laid and the wall frames for the second floor were soon built. |
Late
NovemberHeavy wooden beams and big wooden trusses for the roof are now being lifted into place with a special hoist. |
![]() Late January |
![]() With only a few weeks to go, the scaffolding has gone and the drainlayer is connecting up all the drains. |
|
![]() The finishing touches were put on the outside. |
![]() One of the new upstairs rooms. |
The new library. |
The new Information Communication Technology room. |